Chocorua pump house overhaul 12/20/18
Project Description and Cost Detail
Scope Described
Project is designed to correct inadequate piping and controls at the Chocorua pump house.
Project will place spray foam insulation in station, increasing efficiency for the heat. Upgrade of piping, electrical and SCADA at the Chocorua pump house including addition of 2 meters. Upgrade motor controls on booster pumps, upgrade piping to improve flow efficiency and insure consistency of materials used.
Cost Detail
$30,752.40 as shown on spreadsheet
Funding will be from unexpended proceeds of the $204,930 loan authorized at the 2018 Annual Meeting
All figures are from contractor quotation and equipment price from the supplier