Summit pump house electrical updates 12/20/18
Project Description and Cost Detail
Scope Described
Upgrade to service panel in pump house with addition of 2 meters and pressure transducers for monitoring of the pressure zone and addition of the pressure zone to the SCADA system. Upgrade pump contacts, service panel, surge protection and motor controls for booster pumps. Insulate building with spray foam insulation to increase heating efficiency.
Project is a priority due to the potential inability to supply water to residents at the Summit of Oak Hill should this station be out of service as a result of electrical failure. Project will address code deficiencies at the pump house.
Cost Detail
$30,387.60 as shown on spreadsheet
Funding will be from unexpended proceeds of the $204,930 loan authorized at the 2018 Annual Meeting
All figures are from contractor quotation and equipment price from the supplier