Asset Management Committee

Help Wanted for data collection on Asset Management Program

Individuals needed to verify the location and existing documentation of water system curb stop valves within the Village District of Eidelweiss for an Asset Management Program.

Proficient use of tablet, GPS device, metal detector, and measuring devices required.

Project will include house to house verification of or collection of data.

Please send resume and references to office@69.89.31.68 Please respond by June 30, 2015.

[gview file="http://69.89.31.68/~vdoenhor/wp-content/uploads/2014/11/Eidelweiss-Asset-Management-Project-Plan.pdf"]Eidelweiss Asset Management

Project Plan
Revision 0 - Draft

Written by Larry Leonard – Eidelweiss Commissioner / Team Chairperson – 5/29/2014 [expand title="More Text"]

Table of Contents

Section Description

1 Overview
2 Development Strategy
3 Asset Management Project Team
4 Project Approach
5 Asset Management Implementation
6 Data Collection and Software
7 Implementation Challenges
8 Asset Management Benefits
9 NHDES Grant Programs
10 Work order system
11 Implementation Action Plan
12 Eidelweiss Water System overview
13 Research & Investigation
14 Cost
15 Schedule
16 References / Resources
17 Appendix

Eidelweiss Asset Management

1 - Overview: Asset management as defined by the Environmental Protection Agency (EPA) is maintaining a desired level of service for what you want your assets to provide at the lowest life cycle cost, which means the best appropriate cost for rehabilitating, repairing, or replacing an asset.

The New Hampshire Dept of Environmental Services (NHDES), is encouraging all small water systems in the State to develop an asset management system. The Village District of Eidelweiss with just under 500 homes connected to our water system is such a small water system. In a discussion at the VDOE annual meeting, the residents expressed with an over-whelming acceptance that the village pursue Asset Management.

Asset management planning will help us with decision making regarding the operation, maintenance, and financial planning of our water system and roads.

The Environmental Protection Agency (EPA) is a huge proponent of the process and they have developed a comprehensive set of implementation guidelines, training materials, and software to aide communities in the implementation process.

The New Hampshire Department of Environmental Services (NHDES) has created a new position in their organization called “Asset Management Specialist”. The role of this new staff expert is to promote and assist small community water systems in their asset management implementation. We are working closely with the NHDES and other agencies to bring asset management into focus within the VDOE.

2- Development Strategy: The Environmental Protection Agency (EPA) has set forth five key areas as a framework for effective asset management development:-

1- Current state of assets
2- Required sustainable level of service
3- Identifying critical assets for sustained performance
4- Determine minimum life-cycle costs
5- Develop a long tern funding strategy

The Commissioners of Eidelweiss fully support the need for the Asset Management Plan as a tool to better manage our system and communicate with the community.

The Eidelweiss Asset Management Team was formed by the commissioners in May 2014. The Asset Management Team is empowered to create the project plan, determine the actions, and outline tasks that will be needed during implementation.

As Eidelweiss moves forward with development of the “Asset Management Plan” we will shift from reactionary management to a culture of strategic planning, cost-effective decision making, information sharing, and community involvement.

3- Project Team: The team approach works because it brings together the right people to coordinate and drive the asset management activities and assist the Commissioners in the decision making process.

The Asset Management Team will champion the process of developing the Plan and Philosophy. This does not mean the team will do all the work, but the team will identify the tasks, projects, partnerships, and contractors that will support the implementation.

The team will promote and articulate the benefits of the plan while addressing the core questions of the asset management framework.

Asset management is not a one time, 1 year, or 5 year project, it is a continual, fundamental change in the way infrastructure assets are managed. A high level commitment to the process is required and by forming the asset management team, a fundamental step in that commitment is made.

Attributes of a Successful Asset management Team
1- Has the authority and resources to answer the core questions
2- Flexibility and encourage critical thinking
3- Create opportunities for open sharing of ideas and information
4- Work through problems, share the success, avoid blame
5- Foster an atmosphere that builds trust and partnerships
6- Understands the use of existing elements for the plan
7- Starts implementation during planning to achieve early results

4 - Project Approach: It is important to achieving the benefits, that all aspects of asset management be recognized and included in the implementation plan. This means that while searching and gathering historical data, collecting current asset information, and performing strategic planning that we also use the process to help with prioritizing current water system projects and maintenance issues. The decision making and 2014 water system projects that are implemented will benefit from the in-process Asset Management Process. While large water districts may implement a totally integrated asset management plan, smaller communities like Eidelweiss may select to start with planning, data collection or strategic planning. The Commissioners of the Eidelweiss Village District (VDOE) will oversee the implementation planning of the Asset Management Project; tasks will include:

a- Formation of the “Asset Management Team”
b- Review Project Plans
c- Hiring of consultants
d- Approve funding
e- Provide project management

5 - Asset Management Implementation: Although the completed Asset Management Plan will include both the water system and roads of Eidelweiss, the water system is more complicated, critical to our community and a high priority. Therefore, it has been determined we treat the asset management plan in two (2) parts.

Part “A” - the water system
Part “B” - the roads, driveways, culverts, drainage and facilities.

Although the start of implementation will focus mainly on Part A, (the water system), much of the methodology will also apply to the part B, (the roads and other facilities within the village district).

Key tasks to Implementation (part A):

1- Formation of the “Asset Management Team”

2- Create an inventory of water system physical assets
a- Wells
b- Tanks
c- Pump houses
d- Distribution and Supply lines
e- Curb stops
f- Chemical treatment
g- Supplies and Repair Parts
h- Unique features and other

3- Create an inventory of water system documentation
a- Master Plan
b- Engineering plans
c- Proposed upgrade plans
d- Existing system schematics / maps / GIS
e- Curb stop documentation
f- Repair and service records
g- Other

4- Determine physical assets condition
a- Make, model, age
b- Flow rates (design and actual)
c- Physical condition, operator input, service records
d- Service life (Published data, industry standards, engineer/operator judgment)

5- Determine documentation condition
a- Availability
b- Completeness
c- Accuracy
d- Usefulness

6- Determine Asset Management Plan formats, filing structure, database and software requirements

7- Create a water system operations and maintenance manual

8- Determine required hardware (computer, metal detector, GPS, etc..)

9- Develop “level of service” document

10- Create a work statement (SOW) for Asset Management Plan sub-contract or consultant work as may be needed to assist in:
a- Asset inventory, Condition statements, Probability of failure, Consequence of failure
b- System mapping / GIS / GPS
c- Life cycle costing
d- Financial (Long term funding)
e- Project Management / meetings / training

11- Create bid package / Determine bidders / RFP

12- Review bids & Proposals / Award contract

13- Project Management

14- Review and modification

Key tasks to Implementation (part B): (Roads & Facilities)

1- Review of road conditions
2- Review of drainage and culvert issues / requirements
3- Inventory of equipment and buildings
4- Determine condition of assets
5- Mapping of roads and key features
6- Database of above items
7- Training of employees
8- Short and long term planning of projects
9- Implementation of plan
10- (More to follow)

6 – Data Collection and Software Alternatives: An important aspect of Asset Management Planning is determining the data gathering and field records format. There are many database and software solutions that have been developed and can be employed.

Having new software or computer systems should not interfere with the start of the implementation, this is because simple record keeping in a format that supports data entry into a software package at a later date is sufficient and should be utilized as an initial step.

In the EPA Asset Management handbook, they provide many examples of the data capturing formats and the blank forms which can be used right away. They are in a Microsoft Excel spreadsheet format, so that program can be used to electronically store the data, this format can be imported directly into a database later.

While many providers have designed custom databases for asset management and data collection, seeing the need to have a standardized platform with ease of use, the Environmental Protection Agency has developed the CUPSS database system specifically designed for use by small to medium water systems entering asset management, and it is free. It is supported by downloadable user manuals, training materials, webinars, and NHDES consultants.

The Eidelweiss Asset Management Team will review the CUPSS software database as a possible tool for our database.

We will use a spreadsheet database (see attached- Data Records) to catalog all existing water system data noting level of accuracy, location, file format, and storage location. This will include engineering information, master plan, maps, etc..

A goal would be to enable water operators to utilize handheld field devices to monitor the water system operation and provide key data via those devices during system repair and maintenance.

7 - Implementation Challenges: There are obstacles which may have to be overcome in the implementation of the Asset Management Plan.
Including:
- Determining data collecting methodology
- Determining GPS and GIS system needs
- Working with GIS software for mapping of data
- Changing “focus from operations” to “focus on assets”
- Determining the condition of existing assets
- Gathering and integration of complete and accurate data
- Availability of historical data
- Availability of construction, maintenance and repair records
- Determining life cycle costs
- Hardware and software requirements
- Availability of resources
- Team coordination
- Long term planning vs. short term priorities

8 - Asset Management Plan Benefits: The benefits of the Asset Management Plan will be worth the efforts, challenges and financial commit of the Village District. There will be immediate and long term benefits as implementation tasks are in process.

These benefits will include:
- Immediate benefit in prioritizing current projects
- Immediate benefit of following Asset Management protocol for current projects
- Utilizing a work order tracking and approval system
- Address aging water infrastructure before failure
- Creation of a water systems operations manual
- Improvements to the SCADA system
- Creation of a preventative maintenance program
- A well documented strategic management decision making process
- Improved risk management
- Treat decisions as investment decisions to maximize resources
- More efficient and focused operations
- Choosing capital projects that meet the systems true needs
- Improve system security and safety
- Reduce environmental impacts or violations due to poorly performing assets
- The ability to convey plans clearly to the community
- Improve information sharing and system awareness
- Support to Financial Planning and Budgeting
- Improve water system cost tracking and water rate calculation
- Building partnerships with other water system operations
- Full support of NHDES in our water system planning and management
- Access to lower cost funding and grants

9- New Hampshire Dept. of Environmental Services Grant Programs:

A- Asset Management Grant
The New Hampshire Department of Environmental Services (DES) has an upcoming grant for Public Water System Asset Management Planning. This grant is intended to assist community water systems in developing an asset management plan. The program will provide a 50% matching grant up to $15,000 for water systems to conduct asset management initiatives.

The goals of the Asset Management Planning Grant program are:
1- to initiate an asset management program at community water systems
2- to assist systems in developing an asset inventory with condition assessment
3-to review the current rates and determine if the existing structure supports future investment needs;
4- to communicate these planning efforts to customers and decision makers.
The VDOE will be preparing to summit our application for Asset Management funding.

B- Drawings and Maps Grant
Record drawings are an important tool for efficient and reliable water system operations and maintenance. By maintaining current and accurate plans of the water system infrastructure, especially underground facilities, the system is best positioned to respond to system repairs in the most timely and cost-effective way.

What to Include on record drawings: (Each should have two ties to fixed objects

-All distribution mains, service lines & shutoffs
-All blow-offs, hydrants & valves
-Type, size & depth of pipe
-Other utilities

NHDES DWGB offers a Record Drawing matching grant up to $1,500 to develop or update community system drawings.

A list of firms offering services for record drawings for small public water systems is available at www.des.nh.gov, Publications/Factsheets, DWGB fact sheets # 7-3 and 7-4.

Record drawings are required by DES construction standards Env-Ws 372.33 (small community systems), 373.26 (non-community systems) and operational standards 361.07 (all systems).

C- Leak Detection
The New Hampshire Department of Environmental Services (“DES”) is currently soliciting requests for leak detection surveys from community water systems in New Hampshire. Acoustic leak detection surveys locate leaks using mechanical and electronic listening equipment to detect leakage sounds. Proactive leak detection provides the opportunity to repair leaks early and minimize wasteful water withdrawals, capture lost revenue, and control disruption to the water system.

Project requests will be prioritized on a competitive basis and leak detection surveys awarded to those that demonstrate the greatest potential for water savings and/or provide the most benefit to the water system. The surveys will be funded by DES and completed using a professional leak detection firm.

Project requests must be received by DES no later than July 11, 2014 in order to be considered.

D- SRF Program
The State of NH DWSRF program is a low-interest loan program that assists public water systems with the cost of improving drinking water infrastructure, including new and replacement well sources, treatment and pump house upgrades, storage tanks, water main replacements, new or replacement service water meters, interconnections between two or more existing public water systems, water conservation improvements, and energy efficiency improvements. Eligible public water systems include all community public water systems and non-transient non-profit public water systems. DWSRF projects are ranked based upon the relative impact of the project in achieving the objectives of the Safe Drinking Water Act, protection of public health, water and energy efficiency and affordability of water service. In the future, the State may forgive up to 30% of the loan to communities with Asset Management Planning in place as they currently do for wastewater asset management planning.

The VDOE has sent a preliminary application in for this grant as of June 27, 2014.

10 - Work order system: The use of a work order system is a key element to project planning and updating records in an Asset Management System. The VDOE has implemented a work order management system as of 6/27/2014.
(See the VDOE work order procedure and form)

The VDOE Work Order is used to initiate, track and approve work being performed within the Village District. This will apply to work being performed on the water system, DPW/roads and facilities. Technical and cost information will be filed and used for asset management and budgeting purposes.

11 - Implementation Action Plan: During planning and implementation the ability to track tasks and the status of projects will be paramount to good organization and visibility of actions. The asset management team will be utilizing the newly created “project/actions/tasks” spreadsheet which will be used to keep track of the items to be worked on, list ideas for implementation, assign tasks, and review status of asset management work. This list will be reviewed and updated on a regular basis as new tasks come up and others are completed. (see attached sample)

12- Eidelweiss Water System overview: The Eidelweiss water system is a complex mixture of wells, pump stations, storage tanks, chemical equipment, controls, Scada electronics, valves, pressure reducers, and piping.

The system has seven major elements which we will call stations that consist of well heads, pumps and storage. They are identified as follows:

1- DPW Station: Here we have the primary well head with a 20hp pump producing approximately 175gpm, chemical treatment, and Scada controls main system.
2- Jungfrau Station: Located on Jungfrau Rd at an elevation of 708ft, there is a 5000gal tank, 20hp and 10hp pumps which move water that has come form the main well to the Reinach tanks and Oak Hill pump station. A significant amount of valves, piping, scada and controls reside within the building as well.

3- Muddy Beach Station: Located at Muddy Beach on Pea Porridge Pond are two (2) well heads identified as well#1 (10hp-88gpm) and well#2 (5hp-40gpm). A 5000gal tank, 2 10hp-110gpm pumps, piping, valves, and controls. These wells supply water to the Reinach tanks.

4- Reinach Station: Located at the top of Reinach Rd at 930ft elevation, with two (2) 30,000 gal tanks.

5- Oak Ridge Station: Located part way up Oak Ridge Rd at 777ft elevation, this station houses two (2) 5hp pumps each capable of 54gpm. This pumps water to Chocorua station.

6- Chocorua Station: Located further up Oak Ridge Rd, there is a 5000gal tank and two (2) 5hp-34gpm pumps. Water pumped from Chocorua goes to the summit tanks.

7- Summit Station: Located at the top of Oak Hill at 1242ft elevation. Contained in this large building are 30,000gal and 10,000gal atmospheric tanks and a 5000gal pressurized tank. There are two (2) 5hp-70gpm pumps.

The VDOE water distribution system has nine (9) pressure zones that service homes, there may be homes serviced from piping outside the pressure zones, that is yet to be determined.

The Pressure zones are identified as:
Summit Gravity Chocorua Winnigon
Summit Hydro Aspen Reinach
Rigi Jungfrau Como

The number of homes serviced by each zone is to be determined.

Each of the 7 stations have manual as well as computer controls for operation and reporting of status, tank levels, and flow. The scada system is the computer control, which has PLCs at each location, unique station programming, and radios that send the data to a master PLC and PC located at the office.

The supply and distribution system is made up of miles of pipe of various diameters, Junctions, shut-off valves, and curb stops at the service entrance to each home on the system. There are between 450 to 500 homes serviced.

Asset Management planning will start to determine and document the details of this system.

13- Research & Investigation: Some of the asset management team tasks will include investigating the current water system data, files, history, drawings, maps and the like to catalog known data and seek inputs for the gaps in our information needs.
Additional there is the research that will need to be done to obtain the missing or needed data, contact sources that can be of assistance to us, look at inventory data to complete the evaluation of condition and life-cycle. There may be the need to sub-contract some of the requirements and engage consultants as required. Results of research and investigations will be documented, shared with others, and reviewed at asset management team meetings.

14 - Cost: The cost of developing and maintaining the Asset Management System for Eidelweiss will be a year to year budget requirement. Initially, we have approved an article of $20,000 to get the project planned and into implementation. In addition, there are the already existing funds from the various line items in the main budget. Beyond this year, it will be an ongoing process of updating and improvement as data becomes available, changes are made, improvements are implemented and prioritized needs arise in the water system. There will be some combination of budget line items, warrant articles, rate fees, grants, loans, and reserve funds to support the financial requirements of the plan.

15- Schedule: Asset management as a way of operating, maintaining and managing the VDOE water system will be a ongoing process. It starts now in 2014 and will continue into the future, there is no end date, only intermediate milestone dates and schedule goals that will support the plan and provide Eidelweiss with the required structure to maintain the water system in the most efficient and coat effective manor.

The Commissioners will employ Asset Management Methodologies immediately in our project planning for water system evaluation and improvements this summer. Some projects that come to mind are:

A- Jungfrau pump station
B- Reinach Storage system
C- Muddy Beach well and pump station
D- Oak Hill Pump Station
E- Summit Storage Station
F- Scada System

Schedules are to be determined based on priority, critical needs and budget constraints.

16 – References / Resources:
a- VDOE Water System Master Plan – Fluet Engineering
b- NH Department of Environmental Services (NHDES)
c- US Environmental Protection Agency (EPA)
d- Eidelweiss Scada System Specification & System Drawings
e- Eidelweiss Curb Stop Data - Card file and Digital Files
f- Water Industry Officials Report for Asset Management benefits (EPA)
g- Guide to Supervisory Control and Data Acquisition (SCADA) (NIST)
h- Check up software program for small systems (CUPSS software) (EPA)
i- Water Resource Engineering (McGraw Hill)

17 - Appendix: The following is a preliminary list of references and documents to assist the team in Asset Management. These documents are available online.

1- Asset management handbook (EPA)
2- Asset management best practices (EPA)
3- Handbook for Owners of small water systems (NHDES)
4- Guide to asset management (National environmental services center)
5- Planning for sustainability handbook (EPA)
6- Asset management financial planning grant (NHDES)
7- Sustainability of small public water systems (NHDES)
8- Building an Asset Management Team (EPA)
9- Asset Management development flowchart
10- VDOE Water System Block Diagram (VDOE)
11- Preliminary List of VDOE Water System Maps at Lodge (VDOE)
12- UNH Asset Management Training Information (UNH)
13- Review of Municipal Work Order Systems
14- Review of Municipal Asset Management Systems
16- Asset Management- an ISO 55000 initiative (International Stds. Organization)
17- Water System Operator Roles and Responsibilities- Best Practices Guide (EPA)
18- Energy Efficiency Improvements (EPA)
19- Strategic Asset Management – (HDR Waterscapes)
20- Ohio RCAPO Water System Asset Management Plan (Ohio State)
21- Capacity Planning using Asset Management – (Mass DPW)
22- Check Up Program for Small Systems (CUPSS) - (EPA)
23- Asset Management for Local Officials- (EPA)
24- Water Industry Report of Benefits of Asset Management (USGAO)
25- Asset management Guide – (New Mexico Environmental Finance Center)
26-Implementation Planning for AM- (State of Florida)
27- Record Keeping Rules for Public Water System (EPA)
28- Major Issues in Asset Management Implementation- (Water Research Foundation)
29-Worksheets to capture asset management data- (EPA)
30- Asset management best practices- (State of New Jersey)
31- Best practices for asset management- (US Army Corp of Engineers)
32- Water infrastructure asset management- (CH2MHIL, consulting)
[/expand]

[gview file="http://69.89.31.68/~vdoenhor/wp-content/uploads/2014/11/Asset-Mngmnt-090814.pdf"]VILLAGE DISTRICT OF EIDELWEISS
Asset Management Committee Meeting
September 8, 2014

The Asset Management Committee met at 10:45 am on Monday, September 8, 2014. In attendance were Committee members Larry Leonard, Dinah Reiss, Larry Sodano and Nancy Cole. Also in attendance were Commissioners Ron Sandstrom and Mike Smith, and Engineer Nick Sceggell of Fluet Engineering Associates, a division of Dubois and King. The meeting was taped by Tim Hughes until 12:15 pm. [expand title="More Text"]

At 10:45 am the meeting was called to order by Chairman Larry Leonard.

The water system is discussed. Engineer Nick Sceggell discusses the pressure test done last week at Oak station. The piping upgrades proposed by the engineers and the replacement pumps to be proposed are discussed. Flow meters and use of in line flow meters is discussed. Pump run times and set points, electric usage, and manner in which efficiency savings can be calculated to show the payback of the expenditure that would be required are outlined and discussed. The ability to use a temporary pump that would be located outside of Oak station while the pumps were removed and the proposed new concrete pad was poured and set is discussed. Mike Smith discusses replacing the sump pump for the station at the same time the other work is done. Ron Sandstrom questions in place replacement of the 5 HP pumps at Oak station without the other work being completed. Larry Leonard states that the entire station could be upgraded at one time with and the station would then be done and reliable for the upcoming 15 or more years. Nick Sceggell discusses the benefits to the system overall by updating the entire station at one time. The recommended pumps are Grundfos CR-20. Pricing for this pump will be obtained for review by the Board. Muddy Beach Well #2 and the need to evaluate the pump at this well are discussed. Storage needs for the system and overall daily water usage are outlined and discussed. Investigation of the probable pump failure should not be delayed.

Nick Sceggell discusses the need to have Fluet Engineering Associates update the water model used for the VDOE system. The updated files could be used by the VDOE for creation of the water system portion of the database and maps that are needed. Information in the Water System Master Plan done by Paul Fluet in 2005 is reviewed. Exercising valves is discussed. The need for agreement with a property owner to be able to verify that a curb stop valve functioned properly, which would require entering private property, is outlined. The valves could be turned to verify that they do turn in an “off/on” exercise, but effectiveness of the valve would not be able to be verified without someone present and agreeable to the interruption of service.

Meters, station run times, pressure zones and continued building and development of lots within the VDOE are discussed. The need to increase system efficiency and reliability are discussed, as is the best manner in which to obtain this goal.

At 2:20 pm Larry Sodano makes a motion to adjourn the meeting. Larry Leonard seconds the motion and the motion passed unanimously.

Respectfully submitted,
Nancy E. Cole - Committee member
[/expand]

[gview file="http://69.89.31.68/~vdoenhor/wp-content/uploads/2014/11/Asset-Mngmnt-081114.pdf"]VILLAGE DISTRICT OF EIDELWEISS
Asset Management Committee Meeting
August 11, 2014

The Asset Management Committee met at 10:27 am on Monday, August 11, 2014. In attendance were Committee members Larry Leonard, Jay Buckley, Dinah Reiss, Larry Sodano and Nancy Cole. Also in attendance were Commissioners Ron Sandstrom and Mike Smith, Dave Douglas and Wes Smith of Thorne Surveyors, Joe Rosenberg (resident) and Art Tucker (resident). The meeting was taped by Tim Hughes. [expand title="More Text"]

At 10:27 am the meeting was called to order by Chairman Larry Leonard.

Jay Buckley introduces Dave Douglas and Wes Smith of Thaddeus Thorne Surveyors. Dave Douglas discusses the collection of information within the VDOE and the tying of this information to GPS coordinates. Approximately 10% of the District lots are surveyed on the State Plane Coordinates. Discussion on determining the location of the roads based on lots surveyed to either side of a road is discussed. Marking and location of isolation valves is discussed. The evolution of information as additional lots are surveyed is outlined and discussed. Existing markers for neighboring properties that have been surveyed are checked for with each new survey completed. Use of GPS and difficulties obtaining line of sight to a satellite under the tree canopy of the District is discussed. Software is discussed. Multiple options are available. The ability to build the data onto overlays of the base map is discussed. Gathering of information on the water system, including curb stop valves, isolation valves and water mains is discussed. Existing information is outlined. Wes Smith outlines that the base information and map could be supplied and the VDOE could update and add the text as a means of making the project less costly. Discussion turns to varying GPS devices and the price range for those devices; up to $10,000. The need to obtain a “price for a price” is discussed. The information on hand would need to be made available to Thorne Surveyors. This would be generally reviewed and categorized so that a determination of the amount of information to be obtained could be made. Thorne Surveyors would submit a price to do this determination which, if approved, would result in an estimate to produce the maps. The creation of the initial maps as the largest cost in an asset management program is discussed. Dave Douglas states that a sample section of Eidelweiss Drive could be completed to show the base information and establish general costs that will be incurred with the creation of an asset management database and maps. The information that would be initially reviewed would include the VDOE maps from Fluet Engineering Associates, information on file with Thorne Surveyors, the .pdf database of curb stop valve locations and other documents pertaining to the location of assets. The need for establishment of a budget for asset management annually is outlined and discussed. The need to fund over a number of years and continually update and verify the accuracy of all included information within the asset management system, once developed, is discussed.

At 11:55 am Jay Buckley makes a motion to adjourn the meeting. Larry Sodano seconds the motion and the motion passed unanimously.

Respectfully submitted,

Nancy E. Cole
Committee member
[/expand]

[gview file="http://69.89.31.68/~vdoenhor/wp-content/uploads/2014/11/Asset-Mngmt-072814.pdf"]VILLAGE DISTRICT OF EIDELWEISS
ASSET MANAGEMENT COMMITTEE MEETING
July 28, 2014

The Asset Management Committee met in the District office at 10:10 am on Monday, July 28, 2014. In attendance were Committee members Larry Leonard, Jay Buckley, Nancy Cole and Larry Sodano. [expand title="More Text"]

At 10:10 am the meeting was called to order by Larry Leonard.

The Asset Management Action list is presented and reviewed.

Water operations and water monitoring are outlined and discussed.

The Water System Master Plan is discussed. Recommendations within the Master Plan are to be reviewed for implementation. The project plan for the water system is outlined.

Existing maps are reviewed. Protection of the information regarding valve locations, including curb stop valves, is discussed. Categorizing of the information on hand is needed to determine the areas with the most need for review and updating. Plot plans for deeds located at the Carroll County Registry of Deeds could be used for determining the accuracy of the information on hand. The Town of Madison will be checked with for existence of the original Great Northern development plan maps.

Jay Buckley states that he has met with a local surveyor who is willing to give the VDOE a quote for asset management information. The surveyor has stated that when surveying lots any identified curb stop valves and telephone poles are recorded as landmarks within the survey. The surveyor states that he has much of the information that the VDOE is currently trying to create. Discussion on attempting to identify the percentage of information the surveyor is in possession of is held. Discrepancies have been noted between sets of maps. The cost of the information and maps available is discussed. A meeting could be scheduled with the surveyor for presentation of information samples and discussion on amount of information available and cost for that information. Jay Buckley will work on establishing this meeting.

Discussion is held on software options, compatibility of software, and ability for users to access and update information. Keeping the information in a simple format that is usable is advised. Discussion turns to the use of the Town of Madison map and lot number as the primary identification for each lot within the VDOE when compiling information. Use of names, or linking any information to a property owner, is cautioned against secondary to the amount of homes which sell each year.

Schematics of each pump house are being created by hand at this time. Maintenance scheduling and recording of preventative maintenance is discussed. Planning for future replacements of parts, including pumps, motors and pipes, is needed.

On-line information on GIS mapping and asset management strategies is available. Committee members are encouraged to view this information independently.

Next meeting will be held August 11, 2014 at 10:00 am.

At 12: 25 am Larry Leonard makes a motion to adjourn the meeting. Jay Buckley seconds the motion and the motion passed unanimously.

Respectfully submitted,

Nancy E. Cole
Committee member
[/expand]

[gview file="http://69.89.31.68/~vdoenhor/wp-content/uploads/2014/11/Asset-Mngmt-063014.pdf"]VILLAGE DISTRICT OF EIDELWEISS
ASSET MANAGEMENT COMMITTEE MEETING
June 30, 2014

The Asset Management Committee met in the District office at 10:20 am on Monday, June 30, 2014. In attendance were Committee members Larry Leonard, Jay Buckley, Dinah Reiss, Nancy Cole and Larry Sodano. [expand title="More Text"]

At 10:20 am the meeting was called to order by Larry Leonard.

The agenda is distributed and reviewed.

Information available from NH DES and the federal EPA is outlined. Establishing Asset Management for the District to have in place going forward is discussed. Proper information will allow for desired service levels for the VDOE by enabling planning of service times and replacement times. Project planning around upcoming identified needs will be beneficial. Additional benefits obtained by having the information on all assets documented in a usable format are discussed. Implementation of the new work order procedure is outlined and discussed. The purpose is to obtain written documentation on the completion of every project for inclusion within an asset management database. Discussion on separating the water system and road infrastructure is held. Use of Excel as a beginning point of data gathering is held. Identifying and applying for applicable grants by the Committee is discussed. Possible application for a leak detection grant is being looked at by the Commissioners. Documentation and development of a Capital Improvement Plan are both needed and are both part of an Asset Management Plan. Listing of items to be cataloged to see where gaps exist in information. Documentation for the new pump being installed at Jungfrau will be completed on the work order issued for this project.

Identifying the next meeting date at each meeting is suggested by Jay Buckley.
Weekend access to information is questioned by Larry Sodano.

Dinah Reiss discusses the approved Warrant Article from the VDOE Annual Meeting for creation of a web based asset management system. Dinah Reiss recommends that this Committee review and recommend proceeding with the draft for completion of this project that was submitted to the Board of Commissioners by Mark Graffam earlier this year. Development of a bid package to obtain a price for gathering the information as outlined in this draft could be done. The knowledge of the cost that would be incurred would be beneficial so that all parties are aware. Curb stop locations are discussed. Cataloging this information is outlined. Discussion continues on obtaining data and software available for use in asset management projects. .

Next meeting will be held July 28th at 10:30 am.

Larry Leonard will talk to Ray Seeley about obtaining a sample of the GPS data that he states IWS has collected. Updating of card stock for curb stop valve locations when an error is found is discussed. The .pdf file of all curb stop information on record will be looked into for accessibility. Development of a bid package from the information submitted by Mark Graffam will be looked into. The draft document delivered by Mark Graffam is copied and distributed. Work completed in the 1990’s by Ned Connell that listed roads and culverts is discussed. The information on hand that is being used by the DPW is not complete. Nancy Cole states that she is uncertain if Ned Connell was the developer of this information.

The spreadsheet for pumps within the water system that is available will be distributed.

At 11: 45 am Larry Leonard makes a motion to adjourn the meeting. Jay Buckley seconds the motion and the motion passed unanimously.

Respectfully submitted,

Nancy E. Cole
Committee member