Thusis culvert replacement                                                             12/20/18

Project Description and Cost Detail        

Scope Described

Project incorporates new engineered design.  Project revised so project is 100% on VDOE property.  Project consists of the total replacement of malfunctioning culvert under Eidelweiss Drive and directs the water flow onto VDOE property at Thusis Beach.  All work will be done by the VDOE DPW.  

Cost Detail

24-inch Culvert                                 $614.00

Culvert header                                  $800.00

2 18-inch culverts for outlet        $500.00

Gravel and erosion stone              $500.00

Excavator rental                                $540.00 per day

                Total costs                                                          $2,854.00

                Contingency                                                       $571.00

                Total                                                                      $3,425.00

Remaining balance 2018 article*             -$2,010.00

Total to be raised                                             $1,415.00           

*Of the $7,000 approved at 2018 Annual Meeting, $4,990 was spent in 2018 on updating the engineering.

All figures based on current prices and equipment rental price from the supplier