Project Description and Cost Detail
Scope Described
Project is designed to correct inadequate piping and controls at the Chocorua pump house.
Project will place spray foam insulation in station, increasing efficiency for the heat. Upgrade of piping, electrical and SCADA at the Chocorua pump house including addition of 2 meters. Upgrade motor controls on booster pumps, upgrade piping to improve flow efficiency and insure consistency of materials used.
Cost Detail
$30,752.40
Electrical controls and wiring $6,000
Meters $3,000
Piping $9,850
SCADA panel $4,777
Building Insulation $1,000
Building repairs following piping upgrade $1,000
Contingency $5,125.40
Funding will be from the $140,133.48 unexpended proceeds of the $204,930 loan authorized at the 2018 Annual Meeting
All figures are from contractor quotation and equipment price from the supplier