Como Pressure Reducing Valve (PRV) pit upgrade 12/20/18
Project Description and Cost Detail
Scope Described
Update existing PRV set up with new meter and move set up into new vault from current cement pit.
Allows for improved metering of zone to aid in leak detection and updates valve access when reading meter. Also allows for improved access when an adjustment is needed to the PRV for pressure stabilizing within zone.
Cost Detail
$35,184.00 as shown on spreadsheet
Future Project; not proposed for funding in 2019
All figures are from contractor quotation and equipment price from the supplier